2021 Road Paving Project Update

71st_Roberts_Repave-3
 
 
 
 
 

2021 ROAD PAVING PROJECT UPDATE


 


When the bids for the 2021 Road paving project were opened, the winning bidder was M & J Asphalt, who submitted a winning bid of $419,692.40.  This price was so favorable to the project’s budget that the Village was able to add Cambridge Street and 74th Place east of Sholer Avenue to the list of streets to be repaved in 2021.



Paving is set to begin shortly, working from the north side of the village to the south as follows:



72nd Street, from Roberts Road to 78th Avenue


74th Place, from Roberts Road to 78th Avenue


82nd Place, from Roberts Road to 78th Avenue


Cranbrook Lane


Cambridge Street


91st Street, from Harlem to Oketo Avenue



Saw cutting for curbs on these streets will begin Monday with grinding of streets and curb replacement will be completed as time and crew locations allow.

 
 

« Back

 
Copyright © 2010 Village of Bridgeview. All Rights Reserved.